Vogtle Unit 4 startup date pushed back after motor fault discovered in reactor coolant pump

Vogtle Unit 4 startup date pushed back after motor fault discovered in reactor coolant pump

10.9.2023

The in-service date for Plant Vogtle Unit 4 is being pushed back to 2024 due to a motor fault in one of four reactor coolant pumps, Georgia Power said in a filing to the SEC.

The Oct. 6 filing noted that Southern Nuclear has started the process of replacing the faulty reactor coolant pump (RCP) with an onsite spare one from inventory. The new in-service timeframe is projected for the first quarter of 2024.