24 May 2024
Framatome has been awarded a multi-million-dollar contract to carry out its first major mitigation of buried condenser feed pipes using its innovative spray-in-place structural pipe liner solution at a three-unit operating nuclear plant in the USA.
The company says it will mitigate more than one mile (1.6 km) of large diameter piping running underground to plant condenser boxes. The project will be carried out during nine outages over eight years, with the first application planned in 2025.