PROGRAM AGENDA:
Tuesday, November 17, 2009 Registration: 12:30 – 1:00 p.m.
Course Timing: 1:00 – 4:30 p.m.
Contract Planning and Documentation
- Introduction to Project Management
- Project Documentation
- Electronic Documentation
- Documents Checklist
- Contract
- No Damages for Delay Clause
- No Damages for Delay Exceptions
- Pay When Paid Clause
- Liquidated Damages
- Changes Clause
- Indemnification Provisions
- Purchase Orders
- Lien Waivers
- Records of Events and Requests for Payment
- Change Orders/Amendments
- Management of Project Documentation
- Project Management – Litigation Arbitration Issue
Bidding Issues and Protests Involving Public Projects
- Basic Statutory Framework
- Changes Prior to Bid Opening
- Lowest Responsible and Responsive Bidder
- Refusal to Sign Contract
- Bid Protests
Payment, Liens, and Securitization
- Payment Bond Claims
- Public Payment Bond Claims
Wednesday, November 18, 2009 Continental Breakfast 8:00 – 8:30 a.m.
Course Timing 8:30 a.m. – 4:30 p.m.
Group Luncheon: 12:00 – 1:00 p.m.
Managing Contract Changes
- Changes Clause
- Constructive Changes
- Cardinal Changes
- Claim Components
- Experts and Consultants
- Liability – Warranty of Plans and Specifications
- Defects During Construction
- Theory of Recovery
Claims Identification
- Current Trends
- Arbitration Trends
- Contractual Indemnification Claims
- Claims against Sureties
- Preservation, Damages, Special Issues and Supporting Evidence
- Proof of Construction Damages
- Claim Under Contract v. Claim for Breach of Contract
- Contractual Limits on Liability
- Direct Costs and Overhead
- Delay and Acceleration Claims
- Liquidated Damages
- Attorneys’ Fees and Claim Preparation Costs
- Problems with the Architect
- Avoiding Problems
- Claims Against Architect
- Documenting Disputes
- Defaults in Performance
- Termination
- Securing Lower Tier Performance
- Prompt Payment
- Federal Project Bonds
- Prompt Payment Statutes and Regulations
Construction Damages
- Construction Delay Claims
- Scheduling – Standard CPM Delay Analysis Methods
- Contract Clauses
- Loss of Productivity and Acceleration
- Loss of Productivity Generally
- Factors Affecting Labor Productivity
- Calculation Methods
- Special Issues
- Supporting Evidence
Alternative Dispute Resolution Mechanics
- Dispute Resolution Process
- Dispute Review Board (DRB)
Project Documentation and Electronic Discovery
- What Every Company Should Know
- Electronic Documents
- Spoliation and Document Retention
- Mandatory Preservation of E-Mail
- Electronic Discovery: Attorney and Company Checklist
- Time and Expense
- Safeguarding E-File Production
- Electronic Discovery: Internet Database Management and Document Control
4:30 p.m. :: Course Adjourns |